An elevator is a system that operates closely between devices and needs to follow a certain installation process to ensure safety for users.
Nội dung bài viết
- 1 Family elevator installation process
- 1.1 Step 1: Prepare
- 1.2 Step 2: Close the working platform
- 1.3 Step 3: Close the standard system
- 1.4 Step 4: Install the rail bracket
- 1.5 Step 5: Install rail and align
- 1.6 Step 6: Install the machine
- 1.7 Step 7: Install the counterweight frame
- 1.8 Step 8: Install the frame – cabin floor
- 1.9 Step 9: Install the cable and cable hanger
- 1.10 Step 10: Install the mechanical brake safely
- 1.11 Step 11: Install the floor door
- 1.12 Step 12: Install cabin walls
- 1.13 Step 13: Install additional parts
- 1.14 Step 14: Install electricity
- 1.15 Step 15: Acceptance of static elevator installation
- 1.16 Step 16: Acceptance test run without load
- 1.17 Step 17: Check the ladder
- 1.18 Step 18: Preliminary cleaning
- 1.19 Step 19: Accept test run without load
- 1.20 Step 20: Acceptance of interlock test run with load
- 1.21 Step 21: Verification
- 1.22 Step 22: Acceptance of the elevator and handover for use
Family elevator installation process
Step 1: Prepare
- Check the floor doors, remove obstacles in front of the floor doors, cover and install danger warning signs at necessary locations and on the way up and down.
- Move tools and equipment to the correct construction location (Palan, Tifor, welding machine,…)
- Prepare construction power sources:
- Power source location.
- Mains power capacity.
- Connect electricity to the welding machine and other necessary tools.
- Light up the construction area.
- Install the construction floor, check the connecting cable and put it in the correct position. The construction floor is made with dimensions depending on the well, consisting of many wooden planks > 20 mm thick glued together, the frame uses purlins > (100 x 120) mm.
- Drop safety cables along the stairwell.
- Install Palan in necessary positions.
Step 2: Close the working platform
Step 3: Close the standard system
Step 4: Install the rail bracket
Step 5: Install rail and align
- Install the carbin rail base and counterweight under the pith pit.
- Position the carbine rail and counterweight to the base.
- Install the carbine rails and counterweights next.
- At each position where the carbin rail bracket and counterweight are installed, they will be positioned using ratchet clamps.
- Use wrench 17 to tighten the bolts and nuts with ratchet clamps, then use the rail centering tool and rail offset tool to check the straightness and alignment of the rail compared to the positioned lead wire.
- The distance between the two tops of the carbin rail and the counterweight must not exceed the limit of ±5 mm.
Step 6: Install the machine
- Installation location: engine room.
- Engine room survey
- Use a fully loaded hoist to pull the machine into position.
- Install the I-beam of the machine, the two ends of the I-beam are supported on the stirrups of the elevator pit frame, and there is a gusset plate installed underneath. During the process of installing the two I beams, it is necessary to check the flatness of the two I beam surfaces so that the height between the two surfaces does not exceed 2 mm, then reposition.
- Install the machine chassis and the machine’s cushion shoes.
- Install the machine in the correct position, check the dimensions match the drawings.
- Install the bolts and fix the position of the machine and shoes.
Step 7: Install the counterweight frame
Step 8: Install the frame – cabin floor
Step 9: Install the cable and cable hanger
Step 10: Install the mechanical brake safely
Step 11: Install the floor door
Step 12: Install cabin walls
Step 13: Install additional parts
Step 14: Install electricity
Step 15: Acceptance of static elevator installation
After the complete installation of the elevator, the construction unit, in conjunction with the Supervision Consultant and Project Management Consultant, will conduct acceptance of the installation parts according to the following steps:
- Check installation of equipment in the engine room area
- Check equipment installation in the area along the elevator pit
- Check the installation of cabin equipment
- Check the installation of floor door equipment
Step 16: Acceptance test run without load
Run the elevator without load to check the motor, brake, stop and start, check the opening and closing of the cabin door – each floor door, check the top – bottom limit…
Step 17: Check the ladder
- Run at slow speed to check mechanical details
- Run at slow speed to check the cascading stop flags, upper and lower limits
- Run at high speed and check and correct the position of the floor stop flag and limit switch
Request:
- For floor stop flag: Maximum allowable floor deviation ±10mm
- For limit switches: Maximum top and bottom overruns of 30mm are allowed.
- Check the operation of the switches
- Check out the floor and Cabin displays
Check and try out the features:
- Rescue lights
- Rescue cabinet
Step 18: Preliminary cleaning
Clean elevator equipment, cabins, dirt, and construction mortar during construction (If any).
Step 19: Accept test run without load
After checking the elevator and preliminary cleaning, run the elevator without load and stop picking up each floor to check whether the elevator runs smoothly and stops floors correctly, and check the coordination of the elevator group.
Step 20: Acceptance of interlock test run with load
Run the elevator with load to check the overload parts and the smoothness and accuracy of stopping the elevator at the landing areas and combine to check the elevator group coordination.
Step 21: Verification
Inspect elevators according to state lifting equipment safety regulations to issue a license for use (can be combined at the same time for items 19 and 20).
Step 22: Acceptance of the elevator and handover for use
After inspecting the elevator, thoroughly clean the cabin floor and cabin walls. Check the elevator again by running the elevator at high speed up and down several times, checking the mechanical details to check that the elevator runs smoothly and stops at the correct floor.
HANYANG FACTORY (PHU THO PROVINCE) – Supply 4 generators using
Project: HANYANG FACTORY (PHU THO PROVINCE) Address: Phu Ha Industrial Park – Phu Tho Province...
Mar
YOUNG DIECASTING VINA FACTORY – Supply 2 cargo lifts
Project: YOUNG DIECASTING VINA FACTORY Address: Diem Thuy Industrial Park – Thai Nguyen Province. Implementation...
Mar
FIRST UNION VIETNAM FACTORY – Supply 2 generators, and 4 cargo lifts
Project: FIRST UNION VIETNAM FACTORY Address: Industrial Cluster 1 Thuy Son, Thuy Son Ward, Thai...
Mar
HA QUANG SOCIAL HOUSING – Supply 17 elevators
Project: HA QUANG SOCIAL HOUSINGSSH-07, SSH-08, SSH-09) Address: Nha Trang City – Khanh Hoa Implementation...
Mar
WISTRON INFOCOMM (VIETNAM) CO., LTD (36 Elevators)
Project: WISTRON INFOCOMM (VIETNAM) CO., LTD (36 Elevators) Address: Lot CN09-10, Dong Van 3 Industrial...
Mar
HATECO LA ROMA – Generators
Project: HATECO LA ROMA Address: Lot 4A, Lang Thuong Ward, Hanoi City. Implementation item: Supply...
Mar
Fuji Lift Project – Vinhomes Riverside Long
Fuji Lift Project – Vinhomes Riverside Long Bien Project : Private House Investor ...
Mar
Matiz Lift project – Hoa Binh City
Matiz Lift project – Hoa Binh City Project : Private House Investor ...
Mar